Table of Contents Table of Contents
Previous Page  33 / 54 Next Page
Information
Show Menu
Previous Page 33 / 54 Next Page
Page Background

BCD SPECIAL REPORT ON

HERITAGE RETROFIT

FIRST ANNUAL EDITION

33

such vernacular and humble houses,

some terrible 20th-century replastering,

painting, patch rebuilds and hard cement

pointing had been carried out. There

were even areas of glistening moisture on

interior wall surfaces and large areas were

black with mould. Also, the ground floor

skirting boards had rotted through. At

this point, some basic humidity readings

were taken in June 2015 (Figure 2).

The work began with internal faces of

the exterior walls being stripped of their

coatings and then relined with insulating

and humidity-buffering mineralised

woodchip panels created especially for the

project, and then plaster finished with a

Vivus plaster skim.

Outside, the walls were depointed of

cement and repointed with Vivus mortar

and lime-washed.

It was clearly demonstrated that the

material can be applied quickly. Pure

lime skims were applied and finished

in the same day. The skims contained

no aggregate of any kind nor any other

additive – they were pure air lime. In some

rooms, purely for the experiment, panels

were fitted to the walls and then skimmed

and finished on the same day without issue.

The north- and south-facing external

walls were also finished in the same

timescale, repointing and initial coat

of limewash completed on day one and

subsequent coats applied on day two,

completing the work, front and back –

sunshine with wind (south front) and cold

damp shade (north rear). The two walls

were completed in the same manner,

clearly demonstrating the setting property

of the materials used.

Inside, the walls were paper lined

and then decorated with a modern ‘fully

breathable’ soft paint. Although this will

not affect the insulation per se, it will

undoubtedly reduce the ability of the

walls to absorb humidity. However, many

owners and tenants will expect to be able

to use these finishes, so this was added as

part of the experiment. It is expected that

the house will remain humidity free, even

with the walls lined with paper.

A key element of the demonstration

lay in showing the effect of humidity,

contained within a structure, on the

insulation performance. This moisture can

reduce the effectiveness of any insulation

by up to 30 per cent depending on the

levels. Successfully dry out a building and

maintain that humidity, then it will be

warmer. Take an insulation that buffers

humidity while also helping to equalise

the humidity by being diffusive, and apply

it to a wall that because of its manner

of construction, acts in the same way,

then we will have achieved many things

simultaneously.

The insulation and humidity control

abilities are now being monitored with

sensors installed at the property. The data

taken thus far has shown a very beneficial

effect. The average humidity levels recorded

in the building had dropped 24 per cent

from June 2015 to April 2016, and it is

estimated that the energy efficiency of the

walls has increased by more than 30 per

cent. Empirically, the house is now warm

and dry, even though the building was not

inhabited all winter following the works.

The temperature remains fairly constant,

feeling cool on hot summer days and

warm and dry on damp cold days.

The monitoring will continue for

another two years to show the long term

effect over winters and summers with

the building being regularly used and

inhabited. Feedback from the occupants

will also be sought.

HARRY CURSHAM

(harry@vivus.solution

s)

has spent the past 27 years working with,

experimenting with and learning about

air lime materials. He is a director of Vivus

Solutions Ltd (see page 34). The full Welsh

Government SBRI report is available from

the author on request.

FIGURE 2: Humidity readings – June 2015

AREA

POSITION

HUMIDITY(%RH)

Ground floor

First floor

Internal west wall

Low level

96.35%

88.50%

High level

88.99%

88.50%

Internal north wall

Low level

94.89%

79.50%

High level

78.56%

79.50%

Internal east wall

Low level

93.02%

89.99%

High level

89.90%

89.55%

Internal south wall

Low level

89.95%

88.70%

High level

87.05%

88.70%

Mill Cottage on completion of repointing and lime-washing using Vivus materials

Fireplace and window details, with insulated walls, plastered and finished

Sample data recorded following the work at Mill

Cottage showing a marked fall in dewpoint (black)

and relative humidity (green) from December 2015 to

April 2016, while temperatures (blue) rose. During this

period the house was uninhabited and the weather in

this exposed location was particularly cold and wet.

FIGURE 3